Zimbabwe’s power utility to finish new coal-fired units in 2022

21 Oct, 2021 - 00:10 0 Views
Zimbabwe’s power utility to finish new coal-fired units in 2022

eBusiness Weekly

Bloomberg
Zimbabwe’s state-owned power utility expects to complete the addition of coal-fired units next year, bucking a global trend to reduce reliance on the fossil fuel.

The US$1,5 billion expansion by Zimbabwe Power Company and China’s Sinohydro will finish one unit next year in September and another in December, adding 600 megawatts. That’s intended to replace 920 megawatts of existing capacity prone to breakdowns, according to Forbes Chanakira, site manager for the Hwange Power Expansion project.

The government’s strategy “is to ensure we improve the reliability of the existing coal plant while at the same time embracing renewable technology,” Chankira told Bloomberg in an interview at the plant.

The project, which has been in the works for years, demonstrates how some developing nations will continue burning coal until funding is made available by richer countries to switch to cleaner energy. Neighboring South Africa is also completing some of the world’s biggest stations that run on the fuel and would need US$20 billion to retrofit its fleet to cut pollution.

The Hwange plant in Western Zimbabwe has been flagged for emitting excessive pollutants and a flue gas desulfurization unit will be installed, which will meet World Bank standards, according to Lucia Chibanda, an engineer with ZPC.

China Eximbank will provide a 20-year loan of almost US$1 billion at a 2 percent annual interest rate, Chanakira said. ZPC has to raise US$315 million for project development costs from its own resources and loans from African Export-Import Bank and Standard Bank Group Ltd., he said.

The project is currently 72 percent complete after work slowed due to the Covid-19 pandemic.